Reliance on the Covid-19 Regulations as an Event of Force Majeure

In the recent High Court case of SN Akmida Holdings Sdn Bhd v MTD Construction Sdn Bhd (and Another Originating Summons) [2021] 1 AMR 479, the plaintiff sought to rely on the Prevention and Control of Infectious Diseases (Measures Within Infected Local Areas) Regulations 2020 (‘Regulations’) as an event of force majeure to oppose the defendant’s calls on the two bank guarantees on grounds of “unconscionability”. Although the case turned on several legal issues, our commentary will focus solely on the novel point of one party’s reliance of the Covid-19 Regulations as an event of force majeure in restraining calls on bank guarantees.   
 
Brief facts and findings of the High Court
 
The plaintiff appointed the defendant as the project’s nominated sub-contractor for the construction of two Mass Rapid Transit stations. The plaintiff then provided a performance bond and procured an advance payment guarantee in favour of the defendant, as required by the sub-contract.
 
The defendant subsequently terminated the sub-contract allegedly breached by the plaintiff and demanded payment under both the performance bond and the advance payment guarantee (‘the bank guarantees’). The plaintiff filed two applications to restrain the defendant’s call on the bank guarantees pending arbitration of the dispute. One of the plaintiff’s contentions was that the defendant’s call on the bank guarantees were unconscionable due to an event of force majeure i.e. the enforcement of the Regulations. The plaintiff contended that (i) the enforcement of the Regulations resulted in the plaintiff’s inability to carry out the works; and (ii) it was unconscionable for the defendant’s two calls to be made in view of the enforcement of the Regulations and its three extensions thereafter.
 
The learned Judge, relying on the Federal Court’s decision in Sumatec Engineering and Construction Sdn Bhd v Malaysian Refining Company Sdn Bhd [2012] 4 MLJ 1, held that a party (‘X’) must satisfy two tests, to show that the call on a bank guarantee by its beneficiary (‘Y’) is unconscionable, namely that:
 
  1. X has a “seriously arguable case that the only realistic inference” is Y’s call is unconscionable, or has adduced a “strong prima facie” case that Y’s call is unconscionable; and

  2. X must satisfy the court that the “events or conduct are of such degree such as to prick the conscience of a reasonable and sensible” person. 
The High Court, applying the tests laid down in Sumatec Engineering, was satisfied that the defendant’s calls on the bank guarantees were not unconscionable and dismissed the plaintiff’s applications. The Court held, inter alia, that:
 
  1. The plaintiff has “no seriously arguable case that the only realistic inference” is that the defendant’s calls on the guarantees were unconscionable;

  2. There is no “strong prima facie case” that the defendant’s two calls were unconscionable; and

  3. The events in relation to the termination of the sub-contract and the calls by the defendant were not of such a degree that “prick the conscience of a reasonable and sensible person”.
In arriving at its finding that the calls were not unconscionable, the High Court had to consider inter alia the plaintiff’s reliance on the enforcement of the Regulations as a force majeure event, within the sub-contract provisions. The High Court rejected the plaintiff’s contentions on the following grounds inter alia:
 
  1. The plaintiff’s delay in the works occurred way before the enforcement of the Regulations;

  2. The enforcement of the Regulations does not constitute an event of force majeure within the definition of “Event of Force Majeure” under of clauses 41(a)(i) to (vi) of the sub-contract; and

  3. Even if it is assumed that the enforcement of the Regulations is a force majeure event pursuant to Clause 41(a) of the sub-contract, clause 41(d) stipulates that the ‘event of force majeure’ will not affect the rights and liabilities of the plaintiff and defendant which accrued before the enforcement of the Regulations on 18 March 2020.
Comments
 
This is the first reported case where a party attempts to rely on the enforcement of the Regulations as an ‘event of force majeure’ within contractual provisions.
 
On the facts, it is observed that Clause 41(a) in the sub-contract does not include Acts of Government or ‘outbreak of pandemic, epidemic and/or endemic’ as ‘force majeure’ events. Hence, it remains to be seen if the enforcement of the Regulations will be considered as an event of force majeure if any of the aforesaid events are incorporated as ‘force majeure’ events in the contract between parties.
 
Henceforth, contracting parties should consider revisiting and revising the force majeure clauses in their contracts to include all circumstances within their contemplation as a proactive step in risk management.
 
Case commentary prepared by Jeremiah Ch’ng (Associate) of the Construction and Engineering Practice of Skrine.