Decision of the High Court
The High Court found that the adjudicator did not act in excess of his jurisdiction as the material facts relating to the construction contract were pleaded.
Decision of the Court of Appeal
The Court of Appeal disagreed with the learned High Court Judge and allowed the appellant’s appeals to set aside the adjudication decision and the High Court’s decision allowing the respondent to enforce the adjudication decision.
Whether the adjudicator had acted in excess of his jurisdiction
On the first issue, the Court of Appeal held that the adjudicator had acted in excess of his jurisdiction when he decided on matters that were never raised and pleaded in the payment claim, payment response and all the adjudication pleadings. The Court of Appeal found that clause 36.6 which was not relied upon in the payment claim was a statutory non-compliance with section 5(2)(b) of CIPAA which requires the
“details to identify the cause of action including the provision in the construction contract to which the payment relates” to be included in the payment claim.
Referring to
View Esteem Sdn Bhd v Bina Puri Holdings Bhd [2019] 5 CLJ 479 where the Federal Court made it clear that adjudication pleadings are pivotal, the Court of Appeal held that the failure to plead clause 36.6 in the adjudication claim was fatal to the respondent’s case.
Whether there was a denial of natural justice
On this issue, the Court of Appeal was of the view that the adjudicator had breached the principles of natural justice by unilaterally relying on the unpleaded clause 36.6 of the construction contract in making out a case for the respondent.
The Court of Appeal approved the test applied by the High Court in
Econpile (M) Sdn Bhd v IRDK Ventures Sdn Bhd & another case [2016] 5 CLJ 882 (following the English case of
Cantillon Ltd v Urvasco Ltd [2008] EWHC 282) to determine the issue of breaches of natural justice in adjudication cases, namely that the breach of natural justice must be material (i.e. decisive or of considerable potential importance to the outcome of the dispute) and is not peripheral or irrelevant. The Court of Appeal found that the adjudicator had gone on a frolic of his own and failed to apply the rules of natural justice by failing to notify or bring to the attention of the parties that he was relying on the unpleaded clause 36.6 of the construction contract, which was the basis of his decision to allow the respondent’s claim, without allowing the parties the opportunity to comment or to take their respective stands.
Conclusion
This decision reminds claimants in adjudication proceedings under CIPAA to comply with section 5(2) of CIPAA. It also reminds adjudicators to uphold the principles of natural justice and not to decide on issues that have not been raised by either party in the adjudication unless parties have been given the opportunity to submit on the same. In the event that there is a need for clarification, adjudicators should direct parties to submit on the particular issue that requires clarification before making a decision on such issue.
Case Note by Shannon Rajan (Partner) and Jocelyn Lim Yean Tse (Partner) of the Construction and Arbitration Practice of Skrine.