Court of Appeal Clarifies Distinction Between Late Delivery and Defective Delivery of Vacant Possession
29 October 2026
On 29 August 2026, the Court of Appeal in Mayland Universal Sdn. Bhd. v Kong Aik Weng & Ors [2026] 6 MLRA 751 allowed the Appellant’s appeal against the decision of the High Court dated 5 December 2024 and held that the High Court had erred in law by conflating the time for delivery of vacant possession with the manner of delivery. The Court of Appeal reaffirmed that a breach relating to the manner of delivery does not entitle purchasers to liquidated damages for late delivery under Clause 25(2) of the Schedule H statutory form of sale and purchase agreement prescribed under the Housing Development (Control and Licensing) Regulations 1989 (“Schedule H”).
Background Facts
The developer, Mayland Universal Sdn. Bhd. (“Appellant”), developed a service apartment project known as “Residensi Dorsett Sri Hartamas”. The respondents were purchasers of units in the development (“Respondents”) who had entered into sale and purchase agreements governed under the Housing Development (Control and Licensing) Act 1966 and Schedule H (individually, “SPA” and collectively, “SPAs”). The relevant clauses of the SPA are as follows:
- Clause 25(1) required the Appellant to deliver vacant possession of the parcels within 36 months from the date of the SPA.
- Clause 27 prescribed the manner in which vacant possession was to be delivered, including the requirement that separate strata titles be issued by the appropriate authority.
- Clause 28 permitted the Appellant to apply to the Controller of Housing for written certification authorising delivery of vacant possession notwithstanding that separate strata titles had not been issued for reasons not attributable to the developer.
In August 2018, the Appellant applied to the Controller for certification under Clause 28 of the SPAs. On 25 January 2019, the Controller granted conditional approval permitting the Appellant to deliver vacant possession without the strata titles. Thereafter, between March and June 2019, vacant possession of the units was delivered to the Respondents within the contractual 36-month period.
Notwithstanding that the Respondents had received the keys and physical possession of their respective units within the stipulated timeframe, the Respondents commenced proceedings claiming liquidated damages under Clause 25(2) of their respective SPAs on the basis that vacant possession was incomplete and defective as the separate strata titles had not yet been issued and the Controller's certification was not furnished together with the delivery.
The High Court’s Decision
The High Court held that delivery of vacant possession was incomplete and defective because it was not accompanied by the strata titles or the Controller’s certification. The Respondents were therefore held entitled to compensation for liquidated damages. Dissatisfied with the High Court’s decision, the Appellant appealed to the Court of Appeal.
The issues for determination at the Court of Appeal
The Court of Appeal considered three issues in determining the Appellant’s appeal:
- whether the High Court had erred in conflating the manner of delivery of vacant possession with the time of delivery;
- whether delivery of vacant possession without the strata title constituted a breach of Clause 25 of the SPA; and
- whether an award of liquidated damages would unjustly enrich the Respondents.
The Court of Appeal’s Findings
The Court of Appeal allowed the appeal on the following grounds:
| (i) |
Time of delivery and manner of delivery of vacant possession are distinct concepts |
The Court of Appeal held the High Court had erred in law by conflating the manner of delivery of vacant possession with the time of delivery. In coming to this conclusion, the Court relied on Remeggious Krishnan v SKS Southern Sdn Bhd [2023] 3 MLRA 386, wherein the Federal Court held that “the time frame for delivery of vacant possession is quite separate from the manner of delivery of vacant possession”. A breach in the manner of delivery could not trigger a claim for liquidated damages for late delivery of vacant possession.
In the instant case, as vacant possession had been physically delivered within the stipulated timeframe, i.e. within 36 months, any contention regarding the absence of strata titles and the non-attachment of the Controller’s certification at the time of delivery of vacant possession related only to the manner of delivery of vacant possession under Clause 27 of the SPA and not the stipulated timeframe for delivery under Clause 25 of the SPA.
| (ii) |
Breaches in the manner of delivery give rise to Compensatory Damages, not Liquidated Damages |
The Court of Appeal held that Parliament has provided a saving provision in Clause 28 of the SPA to insulate the vendor or developer from being sued for late delivery of vacant possession as a result of a breach in the manner of delivery of vacant possession. Any claim arising from a defective manner of delivery must be pursued as a claim for compensatory damages. In particular, under Clause 28(4) of the SPA, a purchaser may seek compensatory damages in the event there is a delay by the developer or vendor in handing over the separate strata title after such title has been issued.
The Court of Appeal also held that the Appellant had obtained the Controller's approval before delivering vacant possession, thereby invoking the saving provision in Clause 28(1) of the SPA. Consequently, the Appellant had satisfied its obligations under Clauses 25 and 27 of the SPA.The Court regarded the Appellant’s failure to furnish the Controller’s certification as, at most, a technical or trivial breach of Clause 28(1) of the SPA and such a breach could be compensated with compensatory damages and did not justify the imposition of liquidated damages.
Further, the Court of Appeal held that if the Respondents intend to make a claim against the Appellant with respect to the breach of its obligation to obtain the strata titles, the Respondents could rely on section 74 of the Contracts Act 1950 (“CA 1950”) to seek compensation for any loss caused to them which naturally arose in the usual course of things from the breach.
The Court of Appeal also drew a distinction between compensation for loss or damage caused by breach of contract within the meaning of section 74 of CA 1950 and compensation for breach of contract where a penalty is stipulated for within the meaning of section 75 of CA 1950. The breach in this case falls within the ambit of section 74 of CA 1950.
The Court of Appeal held that the compensation stipulated as liquidated damages in Clause 25(2) of the SPA is meant to compensate a purchaser by way of monetary compensation for
being deprived of the enjoyment and possession of a property which he has paid for in return for a developer’s promise to deliver the property on such stipulated time.
In the present case, the Respondents had received vacant possession and had been enjoying occupation of their units since 2019. A mere technical non-compliance, i.e., failure to furnish the Controller’s certificate together with the delivery of vacant possession, could not reasonably justify compensation within Clause 25(2) of the SPA.
The Court of Appeal added that if compensation is allowed under Clause 25(2) of the SPA on the basis of the Appellant's trivial breach, it would be tantamount to unjustly enriching the Respondents and ignoring the true purpose of Clause 25(1) of the SPA, as the Respondents suffered no actual loss, which is clearly not within the intention of Parliament. In
Obata-Ambak Holdings Sdn Bhd v Prema Bonanza Sdn Bhd & Other Appeals [2024] 6 MLRA 1, the apex court also refused liquidated damages where its operation would unjustly enrich purchasers.
For the reasons stated above, the Court of Appeal allowed the Appellant’s appeal and set aside the High Court’s order.
Conclusion
The Court of Appeal's decision is noteworthy as it provides guidance on the relationship between Clauses 25, 27 and 28 of the Schedule H SPA and the form of claims that arise from the breach of these provisions. The decision also reaffirms the Federal Court’s decision in
Remeggious Krishnan which held that a distinction must be drawn between breaches relating to the timing of delivery and manner of delivery.
Purchasers seeking to claim liquidated damages under Clause 25(2) must establish that vacant possession was delivered outside the contractual timeframe. Mere defects in the manner of delivery, including issues relating to strata titles or supporting documentation, will not automatically trigger entitlement to liquidated damages. Instead, such claims will generally fall within the realm of compensatory damages under the CA 1950 and require proof of actual loss.
The decision also reflects the courts' continued emphasis on preventing contractual remedies from operating in a manner that produces unjust enrichment. For developers, the judgment provides reassurance that technical or procedural non-compliance will not necessarily result in substantial liquidated damages liability where vacant possession has in fact been delivered on time. For purchasers, the decision underscores the importance of demonstrating actual loss where complaints relate to the manner rather than the timing of delivery.
Case Note by Lee Ai Hsian (Partner), Javene Fan Pooi Ling (Senior Associate) and Chong Zhi Shin (Associate) of the Real Estate Practice of Skrine.